Phase 3 -- Custom structures

Phase 3

Tasks include:

1. Construct and install custom caterpillar climb-through and -over tunnel. This task may be a hands-on community construction task that will allow students and volunteers to help create it. 
2. Construct and install concrete embankment, steps, seating, and electrical outlets. The embankment will be concreted to provide stadium style seating and steps along with a stable surface for later safety surfacing. Electrical outlets will be installed to facilitate outdoor learning and experiments.
3. Install custom embankment safety surfacing. The entire concrete embankment area will be coated with a poured-in-place rubber safety surfacing. This safety surface will be designed with various patterns and/or shapes to enhance the overall playground design.
4. Construct and install custom cocoon shaped embankment cargo net climber. The climber will be constructed of similar materials as those shown in the Phase 3 equipment example.
5. Install custom embankment slide. We anticipate that the slide will be constructed similarly to the Phase 3 equipment example.
6. Construct and install overhead moth shade structures. The overhead moths will shade the embankment stadium seating area. We may pursue custom fabric to mimic Cecropia moth patterns if our budget allows for it.